Project Resume

  • ClientTCC / Zuluf Aramco
  • Project LocationZuluf
  • Scope of WorkCable and Wire Laying & OTDR Testing
  • Project DurationAugust 2026 – October 2026
  • Man Hours—
  • Contract Value—
  • Peak Manpower28
  • Major EquipmentPulling Winch, Drum Stand, Cable Roller

Detailed Scope of Work

  • 230 KV HV Cable Laying and Testing
  • OTDR Testing of FO (Fiber Optic) Cable
  • Underground Cable Pulling