3000MW Al-Humaij Solar Project
L&T Renewables / ACWA — Humaij (Near Madinah)
Project Resume
- ClientL&T Renewables / ACWA
- Project LocationHumaij (Near Madinah)
- Scope of WorkElectrical & Instrumentation Works
- Project DurationMay 2026 – October 2026
- Man Hours500,000 Manpower Hours
- Contract ValueSAR 6 Million
- Peak Manpower250
- Major EquipmentCrane 100T/8T/50T, Forklift 10/15T, Manlifts, Generators 900/400/600/125 KVA, Backhoe Loader, Trailers (Low/Flat Bed), Electrical & Instrumentation Testing Equipment
Detailed Scope of Work
- GIS Installation – 1 No
- GIB Installation – 7 Bays
- 13.8KV / 33.8KV Substation Installation, Testing and Commissioning
- Shunt Reactors 100 MVA Installation
- Power Transformer Installation
- Installation of All Other Control and Relay Panels
- Grounding Works
- Cable Tray and Support Installation